WORKPLACE STRATEGY
1. Telecoms Company
2. Top Advertising Agency
3. Software House
4. Marketing Company
5. Training Company

CORPORATE REAL ESTATE
1. Resizing
2. Relocation
3. Lease re-gearing
4. Rationalisation
5. Due diligence & disposal
6. European Portfolio
7. Rationalisation

CAPITAL PROJECTS
1. UK HQ Refurbishment
2. Laboratory Installation
3. Airport Lounge
4. Client Representation
5. Office Re-Configuration

BUILDING CONSULTANCY
1. Building Survey
2. Dilapidations Defence
3. Dilapidations - Industrial
4. Schedules of Condition

PROPERTY and FACILITIES MANAGEMENT
1. Service Realignment
2. Cost Improvement
3. Process Engineering
4. Due Diligence
5. Mobilisation
6. Cost Reduction Plan

 

Case Studies - Capital Projects

1. UK HQ Office Refurbishment -
    Petroleum Company, Uxbridge

Project Goals:

  • £2m capital investment to substantially refurbish high quality offices in 2 phases
  • Provide a high quality environment to help attract the best staff

Results:

  • Organised works to minimise disruption
  • Managed all parties including landlord team
  • All targets (financial & operational) were met
  • Completed in time to integrate new staff into acquired space

[top of page]

2. Laboratory Installation -
    Communications Company, Cambridge

Project Goals:

  • Manage the construction of new testing laboratories for specialist telecoms equipment
  • Oversee design and installation of new electrical sub-station to power high-tech testing facility

Results:

  • Works successfully completed to exacting EU standards
  • Managed within 10% of budget estimate (£60,000)
  • Deadlines for new R & D facility achieved in accordance with business plan and Client 'blue-tooth' projects
  • All business critical procedures met

[top of page]

3. Airport Departure Lounge - US Business Class Airline

Project Goals:

  • Transatlantic departure lounge to be fitted out in two weeks for inaugural flight
  • Inclusion of wi-fi and security systems

Results:

  • Fast track procurement to get the job done and to best value
  • Heavy negotiation of fixed plant and labour rates
  • All statutory and BAA consents obtained

[top of page]

4. Remote Monitoring Centre - Security Company, Glasgow

Project Goals:

  • To provide a newly accredited "gold standard" remote monitoring centre
  • New security products to meet the business' strategic plan
  • Dual purpose attack-proof building to meet high standards

Results:

  • Highly technical specification concealed within standard building fabric
  • Showpiece facility actively used as a sales and marketing tool
  • Completed to detailed specification

[top of page]

5. Office Re-Configuration - Software Company, Bracknell

Project Goals:

  • Create a step change in the culture
  • Reduce occupancy costs
  • Improve staff retention with improved workplace environment

Results:

  • New workspace standards set
  • Re-organisation of departments providing better team working
  • 14% less space supporting 10% more staff
  • 38% reduction in other occupancy costs
  • Improved working environment
  • ROI on capital expenditure achieved in 15 months